Example 1 — Render 20 m²
- thickness 15 mm
- 1800 kg/m³, +5% waste
567 kg
This is a simple scenario that helps estimate the material scale for basic masonry or repair work.
Mortar mass from area × thickness × density, minus openings, plus waste %.
Also useful: cement in mortar, mortar bags needed.
Enter data and click Calculate.
Net area = area − openings. Volume (m³) = net area × thickness. Mass (kg) = volume × density × (1 + waste/100).
567 kg
This is a simple scenario that helps estimate the material scale for basic masonry or repair work.
792 kg
With a larger amount of mortar, it is worth looking not only at volume but also at how the material will be mixed and supplied.
472.5 kg
This example shows that even when the number seems small, mortar is still better calculated in advance than reordered later.
Net area (area minus openings) × thickness = mortar volume in m³; volume × density = mass in kg, then × (1 + waste%). Example: 20 m² × 15 mm, 1800 kg/m³ → 540 kg, +5% → 567 kg.
Cement-lime mortar ~1800 kg/m³, cement mortar ~1600 kg/m³, lightweight ~1500 kg/m³, heavy screed ~2000 kg/m³. Pick the closest or enter a custom value.
Door and window openings, or large unplastered areas, don't need mortar — subtract their area first.
Typical render/plaster coats are 10–20 mm; masonry bedding joints are usually 10–12 mm.
Yes, enter a custom value in the density field — it takes priority over the type preset.
Use the units selector in the header. Field labels, results and examples update automatically when you switch metric ↔ US.
Because it is easy to confuse litres, kilograms, cubic metres, or bags, and that kind of mistake quickly ruins the purchasing estimate.
Most often yes, especially when the substrate or site conditions are less predictable.