Amount of cement in mortar

Cement mass and bags from mortar volume, mix ratio (kg cement per m³) and waste %.

Also useful: mortar requirement, mortar bags needed.

Input data

Custom dosage, waste, bag & price

Results

Enter data and click Calculate.

How the results are calculated

Cement = volume × kg/m³ × (1 + waste/100). Bags = ceil(cement ÷ bag size).

How to use this calculator

  1. Enter mortar volume (volume unit from the header).
  2. Pick a mix ratio (e.g. 1:4) or enter a custom dosage in kg/m³ (SI).
  3. Set waste %, bag size and price.
  4. Calculate to see cement mass, bags and cost.

Usage examples

Example 1 — 1 m³ at 1:4

  • 1.00 m³ × 350 kg/m³
  • +5% waste
  • 25 kg/bag, $20

367.50 kg → 15 bags

A quick estimate of cement mass for a standard 1:4 mix with a modest contingency.

Example 2 — 0.5 m³ at 1:3

  • 0.50 m³ × 430 kg/m³
  • 0% waste
  • 25 kg/bag, $22

215.00 kg → 9 bags

Richer mixes raise cement mass quickly — bags are usually easier for purchasing.

Example 3 — 2 m³ at 1:6

  • 2.00 m³ × 250 kg/m³
  • +10% waste
  • 50 kg/bag, $35

550.00 kg → 11 bags

Shows how waste % and bag size change the purchasing total.

Frequently asked questions

How is cement mass calculated?

Cement (kg) = volume (m³) × kg cement per m³ (from ratio) × (1 + waste%). Example: 1 m³ at 1:4 (~350 kg/m³), +5% → 367.5 kg.

What do the mix ratios mean?

Cement:sand by volume — richer 1:3 mixes use more cement per m³ than lean 1:6 mixes.

Can I override the cement dosage?

Yes, the kg-per-m³ field is editable and takes priority over the ratio preset.

How many bags do I need?

Bags = ceil(cement kg ÷ bag size). A fraction of a bag still counts as a full bag.

Is this cement or ready mortar?

This is cement content within a mortar mix — use the mortar requirement calculator for total mortar mass.

How do I switch metric ↔ US units?

Use the units selector in the header. Field labels, results and examples update automatically when you switch metric ↔ US.

Why is a kilogram result not always enough?

Because cement is usually bought in bags, not in a laboratory-precise kilogram amount.

What should I check after calculating cement?

Most often cost, bag count, and whether the assumptions match the actual construction method you want to use.